The City of Norwalk, under the State Project #102-319 - Rehabilitation of Perry Avenue Bridge over the Norwalk River, will be implementing a One-Way Detour Route on Perry Avenue. The One-Way Detour will begin on Friday, April 20th, 2018. Traffic will be open for eastbound traffic (traveling towards Main Ave). The One-Way Detour Route is expected to last six (6) days.
There will be a Full Road Closure on Thursday, April 26th, 2018 and Friday, April 27th, 2018. The full road closure is expected to last two (2) days for paving operations, weather permitting. Once the paving operation is complete, the road will be open to all traffic with three travel lanes.
Please drive slowly through the area, anticipate delays, and plan your day accordingly. Access to and from your residence/business will not be restricted. If you have any questions, please call Customer Service at 203-854-3200 during their business hours: Monday through Friday from 8:00AM to 4:30PM.